RUN-UP SYNCHRONIZATION

Our team of certified service engineers is well equipped with the latest available testing equipment and tools. The professional team will be there to provide engineering solutions, field commissioning, services and repairs at your disposal.

(On going) Project in Macau for 8 x Easygen 3500 paralleling using run-up synchronization.
The features of run-up synchronization within Easygen 3500

Used to get several synchronous generators onto load in a very short time

Generators are paralleled by closing GCBs during engine start sequence

In some cases the in-rush current of a transformer may be more than one generator can supply when closing the live generator to the dead transformer

Please contact us for more information